The U.S. Government issues a Task Objective Statement (TOS) to both eligible
Contractors (Raytheon and Computer Sciences Corporation (CSC)). The government then provides a one hour briefing of the TOS within five business days of the TOS release. Raytheon
responds with a proposal within 10 business days of the TOS release. The Government selects the winning Contractor between Raytheon and CSC.
The winning Contractor then submits an Independent Cost Estimate (ICE) for accomplishing the assigned task within
three business days. The government and the Contractor, if necessary, negotiate the ICE. Within five business days following
conclusion of the final negotiations related to the ICE, the Contractor submits a Resource Estimate (FN07). Upon government's approval of the FN07, the government then issues a Task Order to commence work.